Project Managment Planning and Execution

INTRODUCTION

Project management refers to the process of planning, organising and managing the activities to be perform in order to accomplish a project successfully. Balfour Beatty plc is an UK based construction company which provide services such as construction, support services and infrastructure investments (Chih and Zwikael, 2015). This project elaborates about the characteristics of project and role of project manager along with theoretical framework and methodology used for project. Apart from this it describes about the composition and management of team in project environment. Further it describe about project management plan, measures used for control & monitor project risk, quality and configuration along with project success or failure status of project.   

Project refers to the set of interrelated act that are planned to be executed within in a fixed period of time over certain cost and limitation in order to achieve particular aim. Balfour Beatty plc is an UK based international infrastructure company provide innovative and efficient infrastructure services.

Project title & Background:-

Company currently working over a 'Office Relocation' project where they want to relocate their current office from London to Manchester. As size of current location is very small and company want to expand its operation by adding new services in their current portfolio such as interior designing. This require company to recruit more manpower to manage their operation, therefore  Balfour Beatty plc decided to move their business. 

Purpose:-

Reason behind relocating the office is to expand its business by adding new service such as interior designing in their current offerings (Eskerod and Vaagaasar, 2014). This require Balfour Beatty to appoint new staffs and adjust extra cabins for them so in order to achieve this aim company decide to shift their office to another location. 

Objective:-

Main aim behind relocation project is to expand workforce of company for adding another service to company's portfolio. Another objective behind moving office to another location is to generate brand identity at new place. 

Scope:-

For accomplishment of project,  Balfour Beatty plc is required to effectively plan and create other department for interior designing. So in order to successfully relocate their business company must ensure that new office should be painted, furnished and carpeted effectively.  

Deliverables:-

Main aim is to develop an interior designing department in company by moving Balfour Beatty plc to another location where infrastructure facilities are more better (Eskerod,  Huemann  and Savage, 2015). In order to accomplish this goal proper schedule is required to develop for performing actions effectively. Apart from this appropriate cost is required to be consider for relocation that includes acquiring a  location for moving company, carpeting, painting and other costs. In addition to this risk involve in project are required to identify and must be communicate effectively to people involve in project. 

Constraints:- 

There are certain issues that are faced by project manager during its execution which are as given below:

  • · Lack of coordination among team members.
  • · Cost incurred for moving the stuff from old office to new is little bit higher as assumed
  • · Time given for execution of project is less as per the activities to be performed

Assumptions:- 

  • Resources that company required to accomplish its task will be available easily.
  • It will require 8 weeks to relocate the office.
  • Material required to complete the project will be easily available to new location. 

Characteristics of a project:- 

A project is consists of certain characteristics that can be better understood from following points:

  • Project is temporary in nature and consists of definite start and end-point.
  • It contains unique set of requirements which is to be fulfilled within the boundaries of project (Floricel and et. al., 2014).
  • This relocation project consists of cross-functional activities because it includes people from various department such as financial, human resources, IT department etc.  

Role of project manager

A person who is responsible for managing and guiding the workforce to perform set of activities in order to accomplish their goal is known as project manager.  They have certain role to perform for executing a project effectively which are as follows:

  • Planning & defining scope:-Under this project manager is responsible for planning the tasks to be performed in order to accomplish goals effectively. Further it includes planing related to resources required, activities to be perform and by whom it is to be perform as well as cost and time required to perform those activities (Gauthier and Ika, 2012). 
  • Risk analysing:- Another role performed by project manager is to analyse the risk involve in execution of project so that future actions can be determine in order to eliminate those risks. 
  • Monitoring and reporting progress:- Project manager is responsible for monitoring the activities performed by its team member in order to guide them so that each activities can be performed as per the plan. Further project manager is also responsible for reporting the progress of project to higher authority that help in determining whether the work is performed in planned direction or require modifications. 

Application of the theoretical frameworks and methodologies within a project environment

Project is a group of activities which are interrelated and performed in order to accomplish a set goal or objective. In order to complete project effectively and achieve positive result a set framework is required which is consists of certain methods, rules and procedures. It is  an overview of activities which guides the which task to be perform and time required by them. Following step are included in the framework within project:

  • Initiation:- Main issue faced by Balfour Beatty plc is that they want to expand their business by adding new services to their current portfolio but they don't have adequate infrastructure or resources at their current office. So they get an idea to move their business at new location which is more specious and rich in infrastructure facilities that support company to perform their operations much effectively. 
  • Planning:- After finalising the idea next step is to plan the activities which are required to be performed in order to achieve set goal (Glukhov, Ilin  and Levina, 2015). Further planning also includes resources, time and cost required to perform each activities. 



SourceWork Breakdown Structure (WBS), 2018)

This picture depict about the project activities are distributed among different small business units. This activity plans are documented by project manager in order describe about activities to be performed, person responsible for performing it, time and cost required to perform  that. 

  • Execution:- Once the activities has been planned and resources are acquired next step is to execute the activities in order to accomplish project on timely manner. Under this step project manager is responsible for guiding their team member related to their task. This help them in performing task effectively.  
  • Control:- Under this step project manager is responsible for monitoring and controlling the activities performed by its team member (Groff and Jones, 2012). Project manager compare the activities performed by workers with planned task in  order to determine the gap between the performance. In case negative result found then proper actions must be taken in order to remove those gap so that performance can be improve. 
  • Closure:- In this set after performing all the activities and achievement of desire result the  project get closed. It is very essential for project manager to analyse each task performed by its team in order to determine that each planned task has been performed effectively  for eliminate future consequences. 

METHODOLOGY

It refers to the systematic and theoretical analysis of methods that can be applied for executing the project effectively.  Methodology help project manager with guidance throughout the project by defining the steps to be taken for completing the task. In order to relocate its office, project manager of Balfour Beatty plc has selected CPM (Critical Path Method) methodology. It refers to a mathematical algorithm which help in analysing, planning and scheduling the projects as it consists of set of activities that are interrelated. Hence it is very essential to analyse and then schedule activities to be perform as per their priorities. Therefore, CPM is a more powerful tool that help project manager in identifying the longest possible path to  perform the project on deadline (Hajdu, 2013). This help in determining early start and finish date after identification of deadline. Following are the steps included in CPM:

  • Identifying activities:- Under this step project manager break the work structure in set of activities along with their time duration and target date using project scope. This help in identifying the activities to be perform for achieving the desire objective and time taken by them.
  • Determining sequences of activities:- After listing up activities next step is to determine the sequence of each activities. It is crucial step as it provide a clear view of connection between the activities and also support in establishing dependencies among these activities. As some activities are depend over the result or completion of another one.  
  • Creating network of activities:- Once the dependencies among activities is identified next step is to create a network diagram (Lappe and Spang,  2014). This critical path figure show the connection between activities based on their dependence.
  • Determining completion time for each activity:- Once the time taken by each activities is determine project manager will be able to identify the time required to accomplish the whole project. 
  • Finding critical path:- Network of activities will help in determining the longest sequence of activities on critical path using four parameters such as early start, early finish, late start and late finish. By finding critical path project manager will be able to manage all its task effectively and on timely manner which help in eliminating any sort of delays.  

The composition and management of teams in a project environment.

Team composition refers to the group of people with certain skills and competencies form up a team in order to achieve common goal. It help in accomplishing the project effectively by properly integrating the skills of team members. So in order to achieve positive outcome of from the execution of project, team management is very essential task of a project manager as effective team is a key to success. Therefore project manager is responsible for composing and management of an effective team that help in accomplishing the desire goal. An effective team consists of following features:

  • Perfect blend of expertise:- An effective team is one which have its team members that are expertise in their field. This help in performing activities with more perfection and also ensure limited  chance of error or failure (Lee and et. al., 2015). Further it is easier to manage people when they are highly skilled as they know methods that will be more appropriate to use for performing particular action. 
  • Team trust:- For composing an effective team it is very essential for project manager to build up trust among its member by maintaining transparency in policies and objectives related to the project. As building up of trust will help in brining positivity among team members and it also support in managing people as trust help in keeping the conflicts away from team members.  

These both are the features of an effective team that help project manager in composing an effective team and which is easier to manage. The project team of Balfour Beatty plc include these features that support project manager to get succeed in its project of office relocation. 

Formulation of project management plan

A project management plan is a detailed classification of elements which are necessary to be executed in order to successfully complete a plan. It is a plan which helps in carry out and execute all the required tasks (Lock, 2016). According to the case scenario of Balfour Beatty, management of this company has decided to relocate their office premises. In order to effectively conduct these tasks, a project management plan has been formulated which is discussed below along with its elements:

Cost – In this element of project management plan, costs that can be involved in organisational operations are involved. These costs can be classified as storage cost, transportation costs, installation costs, maintenance costs and many more. This element is considered as most important as it can help in attaining cost benefit by investing low costs. Balfour Beatty has decided to establish an add on department for interior designing which can help in attaining project benefits at low costs by selecting suitable options for expansion. 

Particulars 

Amount 

Installation cost

3200

Maintenance cost 

600

Training cost 

500

Miscellaneous cost 

150

Total 

4450

Scope – Scope of this project management plan is wider when it comes to development. Expansion of this company will help in attaining higher growth rate and more profitability. In order to maximise the scope, company can take decisions of launching new departments for expansion of the organisational practices. 

Time – To execute and implement the project management plan of Balfour Beatty, time which is considered to be involved is  8 weeks. A time scale consisting classification of activities and their time allocation is developed in this project plan.  

Quality – In order to successfully implement project management plan of relocating the office premises of Balfour Beatty, it is important to use good quality techniques (Madter, Bower and Aritua, 2012). In order to relocate all the office equipments it is important to use transportation services which are reliable and suitable for the business. Quality control is a technique which can be used by this company. 

Communication – It is important to communicate this plan with superiors of the company in order to attain approval so that operations can be done effectively without any delay. 

Risk – There is a moderate amount of risk involved in executing this project management plan. In order to manage involved risk, it is important to identify all the risks so that I can be prevented. By monitoring all the risks levels, there is a possibility that it can be managed at maximum level.  

Resources – In the case of Balfour Beatty, resources are the HR manager and other employees of staff (additional and supporting) which are considered as valuable assets for the company. As they are the individuals which can effectively work together to complete project plan execution. 

Measures to control and monitor project risks, quality, change and configuration

Project risks, quality, change and configuration are required to be controlled and monitored in order to ensure that project plan is appropriate for execution so that organisational objective can be achieved. Various measures to control and monitor these aspects are mentioned below:

Risk assessment – This measure can help in identifying and assessing the intensity of risk which is involved in a project. This measure helps in developing preventive measures which can assist in controlling all the risks. 

Managerial audit – This measures enables management to check the adherence of the tools and techniques which are used by an organisation (Popaitoon and Siengthai, 2014). Under the case scenario of Balfour Beatty, management has decided to relocating their office premises and in order to effectively complete this tasks it is important to check the quality of tools and techniques. This audit can help management of  Balfour Beatty to control and monitor quality of their tools. 

Variance analyses – This is measure in which two variables are evaluated in order to ascertain the change or variances. By using this technique, management of  Balfour Beatty can ascertain reasons behind the change which has occurred. For example: Costs can be analysed to determine its involved changes and it reasons. 

Trend analyses – Project configuration is a process which involves various functions of project life cycle such as processes, tools, methods and many more (Rolstadås and et. al., 2014). The measure of trend analyses can help Balfour Beatty to monitor and control project configuration. This measure can help in ascertaining past trends from which management can analyse and check project configuration elements. 

Evaluation of project success and failure

After preparing project management plan along with identifying various issues and measures, it can be said that this project is successful and has attained success. To justify this statement, there are various evidences which are mentioned as follows:

  • All quality checks and audits are conducted by this company to ensure that there project plan for expansion can be successful. Reliable techniques and methods are used such as risk assessment, trend analyses, variance analyses and managerial audit.
  • Another evidence to justify success of project management plan is effective practices and follow up of plan. Various elements of project plan are considered by the company such as cost, quality, resources, risk and many more which provides an assurance about effectively implementation of project plan (Xiang and et. al., 2012). 

It can be said that Balfour Beatty Limited can effectively expand their organisational operations and can relocate their office premises. 

There are various key learnings which has attained from delivery of this project and they are mentioned below:

  • In order to expand the business premises and business operations of a company it is important to prepare a suitable project management plan as it can help in classifying all the relevant activities according to the nature and level of time required. 
  • Another learning which is attained while developing this project management plan is that every activity of this plan should has a reliable measure to check the adherence of that activity.

CONCLUSION

From the above given report it can be concluded that project management is very crucial activity for a project manager that support in accomplishing the project in effective manner. As team with a proper skills and characteristics with proper coordination help a project manager to perform its planned activities as per given schedule and decided quality. For executing project, a project manager is required to use a methodology which defines step by step execution of project. 

REFERENCES

  • Chih, Y. Y. and Zwikael, O., 2015. Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management. 33(2). pp.352-362.
  • Eskerod, P. and Vaagaasar, A. L., 2014. Stakeholder management strategies and practices during a project course. Project Management Journal. 45(5). pp.71-85.
  • Eskerod, P., Huemann, M. and Savage, G., 2015. Project stakeholder management—Past and present. Project Management Journal. 46(6). pp.6-14.
  • Floricel, S. and et. al., 2014. Extending project management research: Insights from social theories. International Journal of Project Management. 32(7). pp.1091-1107.
  • Gauthier, J. B. and Ika, L. A., 2012. Foundations of project management research: an explicit and sixfacet ontological framework. Project Management Journal. 43(5). pp.5-23.
  • Glukhov, V. V., Ilin, I. V. and Levina, A. I., 2015, August. Project management team structure for internet providing companies. In Conference on Smart Spaces (pp. 543-553). Springer, Cham.
  • Groff, T. and Jones, T., 2012. Introduction to knowledge management. Routledge.
  • Hajdu, M., 2013. Network scheduling techniques for construction project management (Vol. 16). Springer Science & Business Media.

You Also Like This:

Different Stages of Project Management

Development of a Business Plan

Develop Technical Requirements for Business Solutions

Audit Task

Sample About Strategic Management

Assignment on Business Problems

Download Full Sample
Cite This Work To export references to this Sample, select the desired referencing style below:
Copy to Clipboard copy icon
Copy to Clipboard copy icon
Copy to Clipboard copy icon
Copy to Clipboard copy icon
Assignment Prime. [Internet]. Assignment Prime.(2025), Retrieved from: https://www.assignmentprime.com/free-samples/project-management/project-managment-planning-and-execution
Copy to Clipboard copy icon
Boost Grades & Leave Stress

Share Your Requirements Now for Customized Solutions.

Lowest Price
SHP 6.61

Delivered on-time or your money back

100+ Qualified Writers

For Best Project Management Assignment Help

View All Writers
FREE Tools

To Make Your Work Original

  • tools Paraphrasing Tool

    Check your work against paraphrasing & get a free Plagiarism report!

    Check Paraphrasing
  • tools Plagiarism Checker

    Check your work against plagiarism & get a free Plagiarism report!

    Check Plagiarism
  • tools Reference Generator

    Get citations & references in your document in the desired style!

    Generate References
  • tools Grammar Checker Tool

    Make your content free of errors in just a few clicks for free!

    Grammar Checker
  • tools Essay Typer

    Generate plagiarism-free essays as per your topic’s requirement!

    Essay Typer
app
Download App

Avail the Best Assignment Writing Services in Just One Tap!

Add "5% extra off on app"

iphone android
QRcode

 
AP whatsapp

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it. Know more

IT'S OK